IM Flash Technology

The Problem

The team working with IM Flash Technology came to ZELUS to create a plan for off-site prefabrication of MEP materials requiring less plant downtime. They had a massive ramp up with new tool implementations, all while having a very tight timeline. 

 

The Solution

Our team created a plan for off-site prefabrication of MEP materials that required less plant downtime. We were able to identify issues for all stakeholders in advance by using advanced clash detection between the design model and point cloud data, compressing the estimated schedule by almost a week. Additionally, the ZELUS team implemented a BIM Cave where all trades were compliant to the project plan.

Request a Consult

  • Your information will never be shared with any 3rd party providers. Our team may reach out to you as a result of your submission.

Reduced Rework

Reduced rework by 13%

Reduced Timeline

Project schedule condensed by approximately 6%

Reduced Labor Projections

Reduced labor projections by 11%

Reduced Cost

Reduced cost of materials by 16% against budget

Deliverables

point-cloud
Point Cloud
Modeling Services
Revit Model
Rendering
Navis Model

Tools

Modeling Survey
Laser Scanners
autodesk
Autodesk

More Projects

Request a Consult

  • Your information will never be shared with any 3rd party providers. Our team may reach out to you as a result of your submission.